Two Separate Clocks
When a Stalled Kitchen Remodel Counts as Abandoned in Davie
When a stalled kitchen remodel counts as abandoned in Davie depends on two separate 90-day clocks: Florida's contractor abandonment rule and the Town of Davie's permit expiration rule. Florida may presume a project abandoned after 90 consecutive days without work and without just cause, making abandonment grounds for discipline against the contractor's license. Davie's permit expires when work stops or is abandoned for 90 days, or when no inspection is called in within 90 days of the last inspection, putting permit renewal costs on the homeowner's side of the problem. While you wait for the contractor to return, check the date of the last approved inspection and the inspection request history, because the permit clock keeps running too.
- State clock
- 90 days
- Source: F.S. 489.129(1)(j), presumed abandonment and contractor license discipline.
- Permit clock
- 90 days
- Source: Town of Davie Building Division FAQ, citing FBC 105.3.2.1.

- Licensed & insured: CGC1524886
- 500+ kitchens completed
- 2-year workmanship warranty
- Answered 7 AM–10 PM, 7 days
Florida's Clock Applies to the Contractor
Florida treats abandonment as a contractor licensing matter. Under Florida's contractor abandonment statute, F.S. 489.129(1)(j), a project may be presumed abandoned after 90 days if the contractor terminates it without just cause or without proper notice to the owner, including the reason for termination, or fails to perform work without just cause for 90 consecutive days.
The consecutive-day requirement gives the homeowner a specific period to document. Record when work last occurred, keep communications about the interruption, and preserve any termination notice and its stated reason. Those records help establish the sequence of events relevant to the state rule.
The consequence belongs to the contractor's license. Abandonment is grounds for disciplinary action, and the statute allows a presumption of abandonment under its stated conditions.
For a homeowner watching an unfinished kitchen sit idle, that distinction matters. The state clock addresses the contractor's conduct. Your permit has its own expiration conditions, which continue to matter while you seek an explanation or wait for work to resume.
Davie's Clock Applies to the Permit
The Town of Davie's permit expiration and renewal rules establish a separate timeline, citing FBC 105.3.2.1. A permit expires if work fails to start within 180 days, if work starts and then stops or is abandoned for 90 days, or if no inspection is called in within 90 days from the last inspection.
Once construction has started, pay attention to both work activity and inspections. The inspection condition specifically concerns whether an inspection has been called in within the stated period. Obtain the date of the last approved inspection as an objective reference, then check the full inspection history for later inspections and requests.
Renewal has a direct price. Davie assesses 50 percent of the original permit fee when the permit is renewed within 90 days of expiration. After that period, the renewal fee is 100 percent of the original permit fee.
A permit can be renewed once. Further renewal rests with the Building Official.
These are separate milestones: the period that leads to expiration, then the period after expiration that determines the renewal fee. A homeowner waiting for a contractor's return can reach a permit renewal expense while the contractor's licensing issue remains unresolved. Track the permit dates alongside your communications about restarting the kitchen.

Financial Recovery Has Its Own Requirements
Permit renewal and financial recovery address different needs. Renewal concerns the permit for the work; a recovery claim concerns compensation under the applicable requirements.
One condition in Florida's Homeowners' Construction Recovery Fund statute, F.S. 489.141 requires a final judgment from a court of competent jurisdiction in Florida, an arbitration award, or a final order from the Construction Industry Licensing Board directing the licensee to pay restitution to the claimant.
That requirement gives recovery a separate procedural milestone. Reaching 90 days of inactivity relates to the abandonment rule; eligibility for payment from the fund involves the stated judgment, award, or restitution order as one of its conditions.
Keep your contract, payment records, work history, and contractor communications together. Maintain the permit and inspection records alongside them. An organized record lets you identify what happened on the job, what happened with inspections, and which dates need attention as you consider your next step.